During project execution, a project team delivers a project deliverable to the customer. however, the customer neither acknowledges the deliverable nor says if it is acceptable, although an approval is required. what is the best thing to do?
A.Continue with the project
B.Document the situation
C.Contact management for help
D.Call a meeting of the team
Correct
Wrong